Pay Dues

Pflumm Road Improvement Project

Pflumm Road Improvement Project – 143rd St. to 151st St.

Tentative Construction Schedule and Phasing
 Phase 1 from 151st St to south of 147th Terr. Estimated April – July.
 Phase 2 from south of 147th Terr to south of Summit St. Estimated July – September.
 Phase 3 from south of Summit St to 143rd St. Estimated October – December.
 Black Bob Road is the official, signed detour route.
 Intersection work (143rd St and Pflumm Rd and 151st St and Pflumm Rd). There will be work at these intersections though they will remain open to traffic.

 

Meet the Contractor Meeting Handout

Pflumm Expansion Plan

 

 

Historical Information

First meeting slides

Second meeting was held in person Thursday, May 13, 5 – 6 p.m. Church of the Harvest 14841 S. Black Bob Road

Letter to Kevin Gilmore, Councilmember Olathe Ward 3

Response from Kevin Gilmore, Councilmember Olathe Ward 3